Dept. of Trans. PROGRESS Serial No. Contract No. 12-171-05-59 06-0M4004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 81% 06-KER-178-41.6/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 06-20-12 AMD CONSTRUCTION GROUP INC 27285 LAS RAMBLAS SUITE 110 MISSION VIEJO CA 92691 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 445,532.91 200,709.53 2.a. Extra Work 15,261.90 1,150.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 460,794.81 201,859.53 5. Mobilization 6. Total Work Completed 460,794.81 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 460,794.81 201,859.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 201,859.53