Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-256-06-07 06-0M4404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-33-34.3/40.3 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-28-12 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,394,656.32 56,172.00 2.a. Extra Work 12,553.77 12,553.77 b. Adjustment Comp. -57,431.39 -57,431.39 3. Materials on Hand 4. Earned Subject to Retention 1,349,778.70 11,294.38 5. Mobilization 6. Total Work Completed 1,349,778.70 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,339,778.70 1,294.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,294.38