Dept. of Trans. PROGRESS Serial No. Contract No. 13-114-13-06 06-0M9004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 89% 06-KIN-43-17.9/18.6 Federal Project: ACST-P043(41) P Progress payment No. 07 Payment period ending: 04-20-13 AMERICAN PAVING CO P O BOX 4348 FRESNO CA 93744 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 680,373.77 7,770.00 2.a. Extra Work 26,788.86 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 707,162.63 7,770.00 5. Mobilization 80,000.00 0.00 6. Total Work Completed 787,162.63 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 777,162.63 17,770.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,770.00