Dept. of Trans. PROGRESS Serial No. Contract No. 13-056-13-40 06-0N0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 74% 06-KER-5-4.1/ .0 Federal Project: 06-KER-5-R15.8/ .0 ACST-P005(419) 06-FRE-5-60.1/ .0 9E Progress payment No. 06 Payment period ending: 02-20-13 ABHE & SVOBODA INC P O BOX 251 PRIOR LAKE MINNESOTA 55372 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 471,220.57 82,591.27 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 471,220.57 82,591.27 5. Mobilization 193,087.50 0.00 6. Total Work Completed 664,308.07 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 664,308.07 92,591.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 92,591.27