Dept. of Trans. FINAL Serial No. Contract No. 14-035-07-18 06-0N3804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-178-14.3/15.7 Federal Project: CSTP-17D6 Progress payment No. 03 Payment period ending: 10-22-13 GRANITE CONSTRUCTION COMPANY P O BOX 5127 BAKERSFIELD CA 93388 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 454,919.20 -3,390.00 2.a. Extra Work 29,490.98 29,490.98 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 484,410.18 26,100.98 5. Mobilization 20,000.00 0.00 6. Total Work Completed 504,410.18 7. Deductions 0.00 30,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 504,410.18 56,100.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,100.98