Dept. of Trans. PROGRESS Serial No. Contract No. 15-260-10-00 06-0N5604 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 67% Location: Federal Project: 06-KER-58-R94.4 NSNH-P058(120) Progress payment No. 003 Payment period ending: 09-20-15 GRANITE CONSTRUCTION COMPANY 3005 JAMES ROAD BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 523,850.50 17,936.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 523,850.50 17,936.80 5. Mobilization 6. Total Work Completed 523,850.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 523,850.50 17,936.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,936.80