Dept. of Trans. FINAL Serial No. Contract No. 13-105-15-32 06-0N8104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-5-L30.0/L36.4 Federal Project: 06-KER-5-L45.1/L52.0 NONE 06-KER-33-0.0/12.1 Progress payment No. 05 Payment period ending: 11-07-12 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,716,049.66 34,142.00 2.a. Extra Work 15,374.24 6,340.36 b. Adjustment Comp. -24,657.38 -24,657.38 3. Materials on Hand 4. Earned Subject to Retention 3,706,766.52 15,824.98 5. Mobilization 6. Total Work Completed 3,706,766.52 7. Deductions -21,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,685,766.52 15,824.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,824.98