Dept. of Trans. PROGRESS Serial No. Contract No. 16-231-14-31 06-0N9604 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 43% Location: Federal Project: 06-KER-204-5.4/6.7 NHP-P204(5) Progress payment No. 007 Payment period ending: 08-20-16 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC. 2990 BAY VISTA CT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,822,033.07 573,652.50 2. a. Extra Work b. Adustment Comp. -26,669.15 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,795,363.92 573,652.50 5. Mobilization 655,500.00 0.00 6. Total Work Completed 3,450,863.92 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,445,863.92 568,652.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 568,652.50