Dept. of Trans. PROGRESS Serial No. Contract No. 15-233-10-18 06-0P1404 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 25% Location: Federal Project: 06-KER-5-62.5/73.1 NHPI-005-4(195) Progress payment No. 007 Payment period ending: 08-20-15 GRIFFITH/COFFMAN JOINT VENTURE 1128 CARRIER PARKWAY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,396,692.61 1,090,056.28 2. a. Extra Work 69,215.07 2,621.57 b. Adustment Comp. -484,567.55 -86,810.30 3. Materials on Hand 622,862.83 270,176.00 4. Earned Subject to Retention 9,604,202.96 1,276,043.55 5. Mobilization 2,415,092.80 0.00 6. Total Work Completed 11,396,432.93 7. Deductions -50,337.61 -5,355.55 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,968,958.15 1,270,688.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,270,688.00