Dept. of Trans. PROGRESS Serial No. Contract No. 16-112-12-19 06-0P1404 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 58% Location: Federal Project: 06-KER-5-62.5/73.1 NHPI-005-4(195) Progress payment No. 015 Payment period ending: 04-20-16 GRIFFITH/COFFMAN JOINT VENTURE 1128 CARRIER PKWY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,253,548.99 1,669,583.60 2. a. Extra Work 132,482.44 3,298.42 b. Adustment Comp. -978,275.95 -93,666.19 3. Materials on Hand 483,038.46 348,669.13 4. Earned Subject to Retention 19,890,793.94 1,927,884.96 5. Mobilization 2,542,202.95 127,110.15 6. Total Work Completed 21,949,958.43 7. Deductions -73,324.47 -11,176.25 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,359,672.42 2,043,818.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,043,818.86