Dept. of Trans. PROGRESS Serial No. Contract No. 16-295-09-38 06-0P1404 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 88% Location: Federal Project: 06-KER-5-62.5/73.1 NHPI-005-4(195) Progress payment No. 021 Payment period ending: 10-20-16 GRIFFITH/COFFMAN JOINT VENTURE 1128 CARRIER PKWY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,528,089.76 1,891,145.81 2. a. Extra Work 267,765.31 0.00 b. Adustment Comp. -1,303,853.00 -201,464.04 3. Materials on Hand 63,164.50 0.00 4. Earned Subject to Retention 31,555,166.57 1,689,681.77 5. Mobilization 2,542,202.95 0.00 6. Total Work Completed 34,034,205.02 7. Deductions -92,535.46 -21,043.76 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 34,004,834.06 1,668,638.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,668,638.01