Dept. of Trans. PROGRESS Serial No. Contract No. 16-356-13-56 06-0P1404 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 97% Location: Federal Project: 06-KER-5-62.5/73.1 NHPI-005-4(195) Progress payment No. 023 Payment period ending: 12-20-16 GRIFFITH/COFFMAN JOINT VENTURE 1128 CARRIER PKWY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,873,163.21 773,979.75 2. a. Extra Work 268,590.31 825.00 b. Adustment Comp. -1,220,748.98 0.00 3. Materials on Hand 0.00 -63,164.50 4. Earned Subject to Retention 32,921,004.54 711,640.25 5. Mobilization 2,542,202.95 0.00 6. Total Work Completed 35,463,207.49 7. Deductions -633,546.01 -524,494.94 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 34,829,661.48 187,145.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 187,145.31