Dept. of Trans. PROGRESS Serial No. Contract No. 15-294-13-53 06-0P1804 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 80% Location: Federal Project: 06-KIN-5-9.0/16.5 NHPI-005-4(194) Progress payment No. 006 Payment period ending: 10-20-15 GRANITE CONSTRUCTION COMPANY 2716 S GRANITE CT. FRESNO CA 93706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,636,324.19 2,625,887.07 2. a. Extra Work 23,674.33 5,636.33 b. Adustment Comp. -1,327,495.81 -979,662.92 3. Materials on Hand 4. Earned Subject to Retention 10,332,502.71 1,651,860.48 5. Mobilization 1,390,000.00 0.00 6. Total Work Completed 11,722,502.71 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,722,502.71 1,651,860.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,651,860.48