Dept. of Trans. PROGRESS Serial No. Contract No. 17-167-10-55 06-0P2704 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 70% Location: Federal Project: 06-KER-43-16.1/25.1 STP-P043(47) Progress payment No. 003 Payment period ending: 06-20-17 DREAMBUILDER CONSTRUCTION CORP 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 545,947.15 258,404.65 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 545,947.15 258,404.65 5. Mobilization 117,964.35 24,834.60 6. Total Work Completed 663,911.50 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 661,911.50 281,239.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 281,239.25