Dept. of Trans. PROGRESS Serial No. Contract No. 19-233-10-22 06-0P9004 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 52% Location: Federal Project: 06-KER-43-0.1/0.5 SNHG-X029(140) 06-KER-119-17.8/18.5 Progress payment No. 005 Payment period ending: 08-20-19 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,809,249.90 855,636.20 2. a. Extra Work 47,982.86 14,746.51 b. Adustment Comp. 3. Materials on Hand 31,718.00 0.00 4. Earned Subject to Retention 1,888,950.76 870,382.71 5. Mobilization 393,300.00 0.00 6. Total Work Completed 2,250,532.76 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,277,250.76 870,382.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 870,382.71