Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-10-45 06-0P9704 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 13% Location: Federal Project: 06-MAD-152-R0.0/1.1 HSNH-P152(84) Progress payment No. 001 Payment period ending: 03-20-15 GRANITE CONSTRUCTION COMPANY 2716 S GRANITE CT. FRESNO CA 93706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 134,410.10 134,410.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 134,410.10 134,410.10 5. Mobilization 77,500.00 77,500.00 6. Total Work Completed 211,910.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 211,910.10 211,910.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 211,910.10