Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-246-13-12 06-0Q0104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-41-R23.1 NHP-P041-1(124) Progress payment No. 004 Payment period ending: 08-20-15 AMERICAN CIVIL CONSTRUCTORS WEST COAST, INC. 2990 BAY VISTA COURT BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,614,720.25 0.00 2. a. Extra Work 961.31 0.00 b. Adustment Comp. 15,675.00 15,675.00 3. Materials on Hand 4. Earned Subject to Retention 1,631,356.56 15,675.00 5. Mobilization 176,998.00 0.00 6. Total Work Completed 1,808,354.56 7. Deductions -30,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,778,354.56 10,675.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,675.00