Dept. of Trans. PROGRESS Serial No. Contract No. 17-305-11-12 06-0Q0304 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 93% Location: Federal Project: 06-FRE-0-0.0 NONE 06-MAD-0-0.0 Progress payment No. 004 Payment period ending: 10-20-17 ETIC 2285 MORELLO AVE PLEASANT HILL CA 94523 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 373,059.50 24,408.00 2. a. Extra Work 43,894.17 39,133.51 b. Adustment Comp. 532.22 532.22 3. Materials on Hand 4. Earned Subject to Retention 417,485.89 64,073.73 5. Mobilization 79,453.00 0.00 6. Total Work Completed 496,938.89 7. Deductions -30,394.67 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 466,544.22 63,073.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,073.73