Dept. of Trans. PROGRESS Serial No. Contract No. 15-168-14-22 06-0Q2404 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 33% Location: Federal Project: 06-FRE-41-R3.0/M6.1 NHP-P041(125) Progress payment No. 001 Payment period ending: 06-20-15 TEICHERT CONSTRUCTION P.O. BOX 520 FOWLER CA 936250520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 940,490.09 940,490.09 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 940,490.09 940,490.09 5. Mobilization 6. Total Work Completed 940,490.09 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 940,490.09 940,490.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 940,490.09