Dept. of Trans. PROGRESS Serial No. Contract No. 20-203-17-22 06-0Q2804 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 52% Location: Federal Project: 06-KER-99-23.6/R28.4 B1NH-X029(143) Progress payment No. 020 Payment period ending: 07-20-20 BROSAMER & WALL INC 1777 OAKLAND BLVD # #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,462,265.41 1,044,850.03 2. a. Extra Work 464,535.77 168,283.01 b. Adustment Comp. 444,277.62 0.00 3. Materials on Hand 372,703.00 175,269.00 4. Earned Subject to Retention 25,743,781.80 1,388,402.04 5. Mobilization 5,842,500.00 0.00 6. Total Work Completed 31,213,578.80 7. Deductions -59,516.19 -12,065.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,526,765.61 1,376,337.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,376,337.04