Dept. of Trans. PROGRESS Serial No. Contract No. 20-234-14-09 06-0Q2804 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 56% Location: Federal Project: 06-KER-99-23.6/R28.4 B1NH-X029(143) Progress payment No. 021 Payment period ending: 08-20-20 BROSAMER & WALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,746,148.18 1,283,882.77 2. a. Extra Work 844,626.66 380,090.89 b. Adustment Comp. 447,254.43 2,976.81 3. Materials on Hand 148,424.99 -224,278.01 4. Earned Subject to Retention 27,186,454.26 1,442,672.46 5. Mobilization 5,842,500.00 0.00 6. Total Work Completed 32,880,529.27 7. Deductions -92,776.19 -33,260.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,936,178.07 1,409,412.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,409,412.46