Dept. of Trans. PROGRESS Serial No. Contract No. 20-265-13-26 06-0Q2804 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 59% Location: Federal Project: 06-KER-99-23.6/R28.4 B1NH-X029(143) Progress payment No. 022 Payment period ending: 09-20-20 BROSAMER & WALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,117,390.67 1,371,242.49 2. a. Extra Work 988,610.88 143,984.22 b. Adustment Comp. 397,254.43 -50,000.00 3. Materials on Hand 148,425.00 0.01 4. Earned Subject to Retention 28,651,680.98 1,465,226.72 5. Mobilization 5,842,500.00 0.00 6. Total Work Completed 34,345,755.98 7. Deductions -92,776.19 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 34,401,404.79 1,465,226.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,465,226.72