Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 21-130-08-40 06-0Q2804 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 85% Location: Federal Project: 06-KER-99-23.6/R28.4 B1NH-X029(143) Progress payment No. 030 Payment period ending: 04-20-21 BROSAMER & WALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,859,051.10 898,676.50 2. a. Extra Work 1,930,374.54 170,723.46 b. Adustment Comp. 631,353.36 -71,459.02 3. Materials on Hand 375,142.00 0.00 4. Earned Subject to Retention 39,795,921.00 997,940.94 5. Mobilization 6,150,000.00 0.00 6. Total Work Completed 45,570,779.00 7. Deductions -165,769.19 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 45,780,151.81 997,940.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 997,940.94