Dept. of Trans. PROGRESS Serial No. Contract No. 22-025-08-35 06-0Q2804 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 100% Location: Federal Project: 06-KER-99-23.6/R28.4 B1NH-X029(143) Progress payment No. 039 Payment period ending: 01-20-22 BROSAMER & WALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 49,902,985.24 1,092,275.98 2. a. Extra Work 2,866,159.08 224,773.25 b. Adustment Comp. 1,505,388.01 -1,277.49 3. Materials on Hand 47,447.00 -30.00 4. Earned Subject to Retention 54,321,979.33 1,315,741.74 5. Mobilization 6,150,000.00 0.00 6. Total Work Completed 60,424,532.33 7. Deductions -256,457.19 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 60,215,522.14 1,305,741.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,305,741.74