Dept. of Trans. PROGRESS Serial No. Contract No. 22-053-10-52 06-0Q2804 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 99% Location: Federal Project: 06-KER-99-23.6/R28.4 B1NH-X029(143) Progress payment No. 040 Payment period ending: 02-20-22 BROSAMER & WALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 52,075,367.65 2,172,382.41 2. a. Extra Work 2,883,869.08 17,710.00 b. Adustment Comp. 1,434,871.19 -70,516.82 3. Materials on Hand 28,536.00 -18,911.00 4. Earned Subject to Retention 56,422,643.92 2,100,664.59 5. Mobilization 6,150,000.00 0.00 6. Total Work Completed 62,544,107.92 7. Deductions -246,457.19 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 62,326,186.73 2,110,664.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,110,664.59