Dept. of Trans. PROGRESS Serial No. Contract No. 22-080-10-21 06-0Q2804 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 100% Location: Federal Project: 06-KER-99-23.6/R28.4 B1NH-X029(143) Progress payment No. 041 Payment period ending: 03-20-22 BROSAMER & WALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 52,551,293.34 475,925.71 2. a. Extra Work 2,934,541.07 50,671.99 b. Adustment Comp. 1,434,871.19 0.00 3. Materials on Hand 28,536.00 0.00 4. Earned Subject to Retention 56,949,241.60 526,597.70 5. Mobilization 6,150,000.00 0.00 6. Total Work Completed 63,070,705.60 7. Deductions -250,587.19 -4,130.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 62,848,654.41 522,467.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 522,467.70