Dept. of Trans. PROGRESS Serial No. Contract No. 22-264-12-03 06-0Q2804 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 06-KER-99-23.6/R28.4 B1NH-X029(143) Progress payment No. 045 Payment period ending: 09-20-22 BROSAMER & WALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 52,386,677.05 54,413.60 2. a. Extra Work 4,099,927.40 186,427.55 b. Adustment Comp. 2,466,789.92 0.00 3. Materials on Hand 4. Earned Subject to Retention 58,953,394.37 240,841.15 5. Mobilization 6,150,000.00 0.00 6. Total Work Completed 65,103,394.37 7. Deductions -250,587.19 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 64,852,807.18 240,841.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 240,841.15