Dept. of Trans. PROGRESS Serial No. Contract No. 13-238-13-30 06-0Q3604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 28% 06-KER-119-19.7/30.4 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-13 GRIFFITH COMPANY 1128 CARRIER PARKWAY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 983,984.95 983,984.95 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 983,984.95 983,984.95 5. Mobilization 6. Total Work Completed 983,984.95 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 983,984.95 983,984.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 983,984.95