Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-13-13 06-0Q4204 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 90% Location: Federal Project: 06-KER-14-L16.6 NONE Progress payment No. 009 Payment period ending: 04-20-15 MISSION BANK 1450 N. NORMA RIDGECREST, CA 93555 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 931,624.34 30,731.36 2. a. Extra Work 2,043.26 2,043.26 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 933,667.60 32,774.62 5. Mobilization 6. Total Work Completed 933,667.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 933,667.60 32,774.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,774.62