Dept. of Trans. PROGRESS Serial No. Contract No. 14-295-13-00 06-0Q5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 98% 06-FRE-0-0.0/ .0 Federal Project: CSTP-000C(367) Progress payment No. 10 Payment period ending: 10-20-14 ROADWAY ENGINEERING WORKS INC 3442 6TH STREET CERES CA 95307 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,445,328.27 567,874.70 2.a. Extra Work 93,191.37 8,125.92 b. Adjustment Comp. 6,620.00 6,620.00 3. Materials on Hand 452,359.58 -322,218.33 4. Earned Subject to Retention 4,997,499.22 260,402.29 5. Mobilization 596,960.00 0.00 6. Total Work Completed 5,142,099.64 7. Deductions -42,000.00 -42,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,552,459.22 218,402.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 218,402.29