Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-084-09-37 06-0Q5404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-0-0.0 CSTP-000C(367) Progress payment No. 013 Payment period ending: 12-19-14 ROADWAY ENGINEERING WORKS INC 3442 6TH STREET CERES CA 95307 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,045,700.80 129,686.00 2. a. Extra Work 101,029.19 7,837.82 b. Adustment Comp. -17,874.77 -24,494.77 3. Materials on Hand 4. Earned Subject to Retention 5,128,855.22 113,029.05 5. Mobilization 596,960.00 0.00 6. Total Work Completed 5,725,815.22 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,715,815.22 123,029.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 123,029.05