Dept. of Trans. PROGRESS Serial No. Contract No. 14-189-14-51 06-0Q5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 38% 06-FRE-168-0.0/ .0 Federal Project: 06-FRE-180-0.0/ .0 CSTP-X019(27) Progress payment No. 04 Payment period ending: 06-20-14 TABER CONSTRUCTION INC P O BOX 1309 MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,527,217.00 463,732.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 515,917.62 -157,088.45 4. Earned Subject to Retention 2,043,134.62 306,643.55 5. Mobilization 361,000.00 0.00 6. Total Work Completed 1,888,217.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,404,134.62 306,643.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 306,643.55