Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-13-14 06-0Q8004 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 7% Location: Federal Project: 06-KER-58-31.8/39.7 NHP-P059(117) Progress payment No. 002 Payment period ending: 04-20-15 GRIFFITH COMPANY 1128 CARRIER PARKWAY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 262,163.44 75,173.00 2. a. Extra Work b. Adustment Comp. -15,201.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 246,962.41 75,173.00 5. Mobilization 6. Total Work Completed 246,962.41 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 246,962.41 75,173.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 75,173.00