Dept. of Trans. PROGRESS Serial No. Contract No. 14-169-14-26 06-0Q8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 51% 06-KER-0-0.0/ .0 Federal Project: CSTP-X029(111) Progress payment No. 02 Payment period ending: 06-20-14 NORTHWEST PAVING 8115 SECLUDED VALLEY DRIVE REDDING CA 96001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 866,219.51 443,700.04 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 866,219.51 443,700.04 5. Mobilization 126,939.95 26,724.20 6. Total Work Completed 993,159.46 7. Deductions -2,787.40 -2,787.40 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 990,372.06 467,636.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 467,636.84