Dept. of Trans. PROGRESS Serial No. Contract No. 22-356-15-25 06-0Q9204 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 54% Location: Federal Project: 06-KER-99-10.4/21.2 ACNH-P099(660) Progress payment No. 015 Payment period ending: 12-20-22 GRIFFITH-ATKINSON JV 1128 CARRIER PKWY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,758,141.57 752,996.81 2. a. Extra Work 356,994.59 97,305.29 b. Adustment Comp. 375,959.99 10,268.48 3. Materials on Hand 2,262,787.67 184,184.00 4. Earned Subject to Retention 27,753,883.82 1,044,754.58 5. Mobilization 5,300,000.00 0.00 6. Total Work Completed 30,791,096.15 7. Deductions -317,779.50 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,736,104.32 1,034,754.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,034,754.58