Dept. of Trans. PROGRESS Serial No. Contract No. 23-298-11-25 06-0Q9204 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 99% Location: Federal Project: 06-KER-99-10.4/21.2 ACNH-P099(660) Progress payment No. 025 Payment period ending: 10-20-23 GRIFFITH-ATKINSON JV 1128 CARRIER PKWY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,232,916.65 2,000,614.41 2. a. Extra Work 2,775,210.84 290,818.52 b. Adustment Comp. 1,045,162.56 0.00 3. Materials on Hand 66,466.00 -134,107.00 4. Earned Subject to Retention 43,119,756.05 2,157,325.93 5. Mobilization 5,300,000.00 0.00 6. Total Work Completed 48,353,290.05 7. Deductions -322,779.50 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,096,976.55 2,147,325.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,147,325.93