Dept. of Trans. PROGRESS Serial No. Contract No. 24-053-15-25 06-0Q9204 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 99% Location: Federal Project: 06-KER-99-10.4/21.2 ACNH-P099(660) Progress payment No. 029 Payment period ending: 02-20-24 GRIFFITH-ATKINSON JV 1128 CARRIER PKWY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,126,430.01 674,356.32 2. a. Extra Work 3,406,016.97 353,617.86 b. Adustment Comp. 1,103,428.06 42,016.50 3. Materials on Hand 4. Earned Subject to Retention 45,635,875.04 1,069,990.68 5. Mobilization 5,300,000.00 0.00 6. Total Work Completed 50,935,875.04 7. Deductions -342,779.50 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 50,593,095.54 1,059,990.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,059,990.68