Dept. of Trans. PROGRESS Serial No. Contract No. 22-203-14-48 06-0R1904 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 39% Location: Federal Project: 06-KER-223-R15.7/R16.3 CSTG-X029(150) 06-KER-184-L0.0/L0.3 CML-6206(32) Progress payment No. 003 Payment period ending: 07-20-22 GRIFFITH COMPANY 1128 CARRIER PKWY AV BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 906,891.22 297,984.38 2. a. Extra Work 3,621.55 3,621.55 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 910,512.77 301,605.93 5. Mobilization 239,228.55 0.00 6. Total Work Completed 1,149,741.32 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,149,741.32 301,605.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 301,605.93