Dept. of Trans. PROGRESS Serial No. Contract No. 23-082-09-46 06-0R1904 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 98% Location: Federal Project: 06-KER-223-R15.7/R16.3 CSTG-X029(150) 06-KER-184-L0.0/L0.3 CML-6206(32) Progress payment No. 009 Payment period ending: 03-20-23 GRIFFITH COMPANY 1128 CARRIER PKWY AV BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,736,161.83 -6,395.78 2. a. Extra Work 89,710.21 29,677.07 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,825,872.04 23,281.29 5. Mobilization 318,971.40 0.00 6. Total Work Completed 4,144,843.44 7. Deductions -225.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,144,618.44 23,281.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,281.29