Dept. of Trans. PROGRESS Serial No. Contract No. 24-170-10-56 06-0R2104 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 90% Location: Federal Project: 06-MAD-41-6.3/9.2 ACNH-P041(603) Progress payment No. 014 Payment period ending: 06-20-24 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,265,809.41 1,207,961.48 2. a. Extra Work 26,963.17 0.00 b. Adustment Comp. 208,099.38 0.00 3. Materials on Hand 61,761.54 -78,760.95 4. Earned Subject to Retention 9,562,633.50 1,129,200.53 5. Mobilization 1,300,000.00 0.00 6. Total Work Completed 10,800,871.96 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,852,633.50 1,129,200.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,129,200.53