Dept. of Trans. PROGRESS Serial No. Contract No. 15-238-09-11 06-0S2604 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 20% Location: Federal Project: 06-KIN-41-17.1/R39.9 NHP-P041(126) Progress payment No. 001 Payment period ending: 08-20-15 PAPICH CONSTRUCTION COMPANY, INC. PO BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 339,598.42 339,598.42 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 339,598.42 339,598.42 5. Mobilization 86,514.73 86,514.73 6. Total Work Completed 426,113.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 426,113.15 426,113.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 426,113.15