Dept. of Trans. PROGRESS Serial No. Contract No. 16-141-09-40 06-0S2804 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 62% Location: Federal Project: 06-KER-58-R136.0/R143.8 NHP-P058(123) Progress payment No. 006 Payment period ending: 05-20-16 PAVE-TECH INC 2231 LA MIRADA DRIVE VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,713,262.00 2,317,356.17 2. a. Extra Work 23,173.59 825.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,736,435.59 2,318,181.17 5. Mobilization 116,880.00 29,220.00 6. Total Work Completed 2,853,315.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,853,315.59 2,347,401.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,347,401.17