Dept. of Trans. FINAL Serial No. Contract No. 21-355-08-27 06-0S3114 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-TUL-190-R15.1/16.9 NONE Progress payment No. 028 Payment period ending: 07-19-21 WABO LANDSCAPE & CONSTRUCTION INC 726 ALFRED NOBEL DR HERCULES CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 269,549.00 0.00 2. a. Extra Work 2,942.96 0.00 b. Adustment Comp. 1,843.06 1,843.06 3. Materials on Hand 4. Earned Subject to Retention 274,335.02 1,843.06 5. Mobilization 30,000.00 0.00 6. Total Work Completed 304,335.02 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 304,335.02 11,843.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,843.06