Dept. of Trans. PROGRESS Serial No. Contract No. 16-298-10-13 06-0S4304 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 48% Location: Federal Project: 06-FRE-0-0.0 NONE Progress payment No. 005 Payment period ending: 10-20-16 CENTRAL VALLEY ASPHALT 23494 RD 196 LINDSAY CA 93247 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 613,214.76 157,101.02 2. a. Extra Work 11,180.40 11,180.40 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 624,395.16 168,281.42 5. Mobilization 8,800.00 0.00 6. Total Work Completed 633,195.16 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 633,195.16 168,281.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 168,281.42