Dept. of Trans. PROGRESS Serial No. Contract No. 20-356-13-48 06-0S4604 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 59% Location: Federal Project: 06-FRE-99-R0.9/R5.0 ACNH-P099(644) Progress payment No. 009 Payment period ending: 12-20-20 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,628,172.80 -753,539.25 2. a. Extra Work 2,317,207.67 1,427,543.52 b. Adustment Comp. 497,557.64 183,888.77 3. Materials on Hand 141,660.00 -50,955.00 4. Earned Subject to Retention 16,584,598.11 806,938.04 5. Mobilization 2,823,000.00 141,150.00 6. Total Work Completed 19,265,938.11 7. Deductions -160.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,407,438.11 948,088.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 948,088.04