Dept. of Trans. PROGRESS Serial No. Contract No. 21-297-13-41 06-0S5104 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 14% Location: Federal Project: 06-KER-223-21.2/21.2 HSST-S223(12) HSIP-6206(29) Progress payment No. 002 Payment period ending: 10-20-21 GRIFFITH COMPANY 1128 CARRIER PKWY AV BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 166,900.89 154,354.14 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 166,900.89 154,354.14 5. Mobilization 154,154.03 154,154.03 6. Total Work Completed 321,054.92 7. Deductions -23,073.00 -23,073.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 297,981.92 285,435.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 285,435.17