Dept. of Trans. PROGRESS Serial No. Contract No. 19-291-14-21 06-0S5504 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 65% Location: Federal Project: 06-KER-99-32.4 ACNH-P099(620) Progress payment No. 005 Payment period ending: 10-20-19 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 793,691.94 253,166.11 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 793,691.94 253,166.11 5. Mobilization 161,789.92 8,089.50 6. Total Work Completed 955,481.86 7. Deductions -15,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 940,481.86 251,255.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 251,255.61