Dept. of Trans. PROGRESS Serial No. Contract No. 20-056-11-16 06-0S5504 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 100% Location: Federal Project: 06-KER-99-32.4 ACNH-P099(620) Progress payment No. 009 Payment period ending: 02-20-20 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,162,325.63 29,938.92 2. a. Extra Work 113,350.85 52,855.34 b. Adustment Comp. -60.07 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,275,616.41 82,794.26 5. Mobilization 161,789.92 0.00 6. Total Work Completed 1,437,406.33 7. Deductions -177,000.00 -74,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -18,881.92 -8,279.43 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,241,524.41 514.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 514.83