Dept. of Trans. PROGRESS Serial No. Contract No. 20-080-08-50 06-0S5504 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 100% Location: Federal Project: 06-KER-99-32.4 ACNH-P099(620) Progress payment No. 010 Payment period ending: 03-20-20 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,346,648.54 184,322.92 2. a. Extra Work 113,350.85 0.00 b. Adustment Comp. -60.07 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,459,939.32 184,322.92 5. Mobilization 161,789.92 0.00 6. Total Work Completed 1,621,729.24 7. Deductions -347,000.00 -170,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 18,881.92 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,274,729.24 33,204.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,204.84