Dept. of Trans. SEMI-FINAL Serial No. Contract No. 21-109-08-16 06-0S5504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-99-32.4 ACNH-P099(620) Progress payment No. 015 Payment period ending: 04-30-20 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,408,061.27 0.00 2. a. Extra Work 143,417.58 0.00 b. Adustment Comp. -247.27 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,551,231.58 0.00 5. Mobilization 161,789.92 0.00 6. Total Work Completed 1,713,021.50 7. Deductions -200,000.00 4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,513,021.50 4,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,000.00